Kyivteploenergo will buy 15 cogeneration units with total capacity of 60.5 MW for UAH 1.125 bln
The municipal enterprise Kyivteploenergo has identified KTS ENGINEERING (Slovakia) as the winner of the tender for the purchase of 15 sets of new cogeneration units with a total capacity of 40.5 MW.
According to the announcement in the ProZorro e-procurement system, the cost of the agreement will be UAH 1.125 billion with the expected purchase cost of UAH 1.262 billion.
Delivery time for nine sets of Austrian Jenbacher JMS 624 GS-N.L units with a capacity of 4.5 MW each and six sets of Jenbacher JMS 620 GS-N.L. with a capacity of 3.333 MW each - until December 31, 2025.
The electrical efficiency of JMS 624 operating on natural gas is 46.9%, thermal efficiency - 42.4%, JMS 620 - 45.4% and 43%, respectively.
Advertising
Advertising
MORE ABOUT
Unknown persons fire at Kyivteploenergo facility in Holosiyivsky district
17:06, 01.04.2025
Kyivstar supervisory board approves deal to acquire Uklon for UAH 7.25 bln
21:01, 20.03.2025
Payments to Kyiv budget from ProZorro auction sales increase by 30 times – budget commission member
18:27, 19.03.2025
Kyivteploenergo repairs nearly 600 heat supply system failures in Feb
13:59, 10.03.2025
Ukrainian city of Zaporizhia receives 12 cogeneration units from intl partners
09:32, 27.02.2025
LATEST
Kallas: Coalition of the Willing discusses format of possible mission in Ukraine
21:08, 10.04.2025
Some 73,000 Ukrainian military personnel complete training in EU – mission
20:35, 10.04.2025
UNBROKEN plans to complete reconstruction of rehabilitation center in Briukhovychi, Lviv region, in Nov
20:26, 10.04.2025
Enemy activity increased in Toretsk and Pokrovsk directions
20:25, 10.04.2025
Ukraine and Australia discuss strengthening defense and security cooperation