DTEK to help Khersonoblenergo with repair work to remove network restrictions from Tryfonivska SPP
DTEK Energy Holding has offered JSC Khersonoblenergo assistance in carrying out repair work at one of the company's substations, which will help remove network restrictions from the Tryfonivska SPP and increase electricity generation at the plant.
"The plant still has network restrictions on power output in the amount of 2 MW. It is due to the need to complete repairs at the Khersonoblenergo substation. To speed up this process, DTEK specialists offered their help," the energy holding said on its Telegram channel on Tuesday.
Currently, DTEK Renewables specialists continue to restore the Tryfonivska SPP, which was damaged during the occupation: 50% of the plant's capacity has already been restored.
"Now, the solar power plant can generate 5 MW from its installed capacity of 10 MW," the company said.
Advertising
Advertising
MORE ABOUT
AMKR plans to expand cooperation with Foundry, Mechanical Plant in repair of dump cars in 2026
19:18, 12.01.2026
Norway announces DKK 4 bln aid package for Ukraine, particularly in energy sector
19:16, 12.01.2026
Russian attack leaves 33,500 families in Odesa region without electricity – DTEK
10:47, 12.01.2026
Electricity restored to 200,000 subscribers in Dnipropetrovsk region - DTEK
13:36, 08.01.2026
Power restoration for over 9,000 Vyshgorod district consumers to take more time after Saturday’s attack – DTEK
16:50, 29.12.2025
LATEST
GUR: Russia considering options for striking Ukrainian NPP substations
16:55, 17.01.2026
Zelenskyy imposes sanctions against Russian paralymical committee, Russian computer sports federation, three individuals
16:52, 17.01.2026
Shmyhal: Lithuania preparing govt decision on allocating additional energy aid to Ukraine
16:35, 17.01.2026
Critical infrastructure facility in Kharkiv significantly damaged by enemy shelling - mayor
16:21, 17.01.2026
Zelenskyy announces decisions taken to increase electricity imports