DTEK reports another shelling of its frontline TPP
On January 4, as a result of shelling by Russian aggressors, DTEK's frontline thermal power plant, which had been subject to repeated attacks previously, was once again damaged.
According to DTEK's Telegram channel on Friday, according to preliminary information, there were no casualties, but the plant's equipment was seriously damaged.
"After the shelling ceased, the power engineers began to eliminate the consequences of the attack," the statement said.
DTEK noted that over the past two and a half months, the enemy has carried out more than a dozen attacks on the station, during one of which five power engineers were injured.
As reported, earlier that day the Ministry of Energy reported shelling of a thermal power plant in Donetsk region, because of which one of its units was switched off.
Advertising
Advertising
MORE ABOUT
DTEK's digitalization boosts power line defect detection to 98%, greatly reduces repair time
19:27, 11.03.2025
Iceland contributes additional over EUR2 mln to Ukraine Energy Support Fund
10:09, 11.03.2025
Ukraine's energy sector losses from Russian strikes surpass $20 bln – Energy Club VP citing RDNA4
20:49, 07.03.2025
Russia damages DTEK Energy facility in Ukraine's Dnipropetrovsk region
16:28, 07.03.2025
DTEK gas production facilities in Poltava region attacked by Russia stop working due to damage
12:34, 07.03.2025
LATEST
Some 30 projects within NEFCO Green Recovery Program for Ukraine completed
10:42, 14.03.2025
Third group of REDpreneurUA program launched: support and development of existing business in Ukraine – URCS
19:57, 12.03.2025
Ukrainian oil company Ukrnafta integrates ERP system to automate key business processes
14:05, 12.03.2025
Ukrainian delivery operator Nova Poshta to audit processes as part of structural overhaul
13:35, 12.03.2025
Russia's National Wealth Fund could be depleted within 1 year if oil prices fall to $45-$47 per barrel – Ukrainian diplomat