Ukrenergo to reconstruct 18 substations' transformers this year
National Power Company Ukrenergo plans to reconstruct 18 automatic transformers at 12 substations this year.
The company's press service reported that the transformer program approved in 2016 foresees the replacement and installation of 52 transformer equipment units, which reached the end of their lifespan (25-30 years) and have been operating for over 40 years.
This year, the company has already replaced two automatic transformers at the 330 kV Rivne and Poltava substations and installed new AT-4 transformer at the Kremenchuk 330 kV substation.
"Updating the main equipment of the substations significantly increases the reliability of the transmission system, and for some projects it can increase the overall transformer capacity of the substations, directly influencing the operational safety of the power grid and the possibility of regional development," the Ukrenergo's press service said.
As reported, the European Bank for Reconstruction and Development (EBRD) can provide Ukrenergo EUR 149 million for a project to upgrade transmission networks.
Advertising
Advertising
MORE ABOUT
On Monday, Ukrenergo will apply electricity restrictions in all regions of Ukraine
09:12, 12.01.2026
Emergency blackout in Kyiv halts water supply, electric transport – Kyiv authorities
13:22, 10.01.2026
Online application portal for U.S.–Ukraine Reconstruction Investment Fund launched
11:44, 08.01.2026
Another Russian drone attack leaves many consumers in Dnipropetrovsk region without electricity - Ukrenergo
14:59, 07.01.2026
Some 423 MW of new balancing capacity already added to power system after first 2 special auctions – Ukrenergo
13:27, 02.01.2026
LATEST
Ukrainian Lobbyists Association supports govt's initiative on new Labor Code as systemic labor market reform
19:54, 09.01.2026
Ukrainian Court upholds lawsuit by potential bidders in competition to select asset manager for IDS Ukraine
19:37, 09.01.2026
Ministry of Energy instructed to increase reserves of natural gas, repair materials – Svyrydenko
20:19, 08.01.2026
Svyrydenko: Additional 911 MW released to grid after reviewing critical infrastructure list
18:55, 08.01.2026
EBRD provides OTP Leasing with local-currency equivalent of EUR 20 mln loan to support MSMEs