Ukrenergo, Transparency International, CoST agree on monitoring of projects
Ukrenergo has signed a memorandum with NGOs Transparency International and CoST (Construction Sector Transparency Initiative) on monitoring the use of funds in the framework of its projects.
According to an Interfax-Ukraine correspondent, the relevant document was signed in Kyiv on October 27.
"The memorandum provides for accountability of all the phases of the project according to international standards, verification of information by a group of independent consulting engineers," the press service of Ukrenergo said.
A pilot project within cooperation will be the installation of the third 330/110/35 kV autotransformer at the Chernivtsi substation.
Advertising
Advertising
MORE ABOUT
On Monday, Ukrenergo will apply electricity restrictions in all regions of Ukraine
09:12, 12.01.2026
Emergency blackout in Kyiv halts water supply, electric transport – Kyiv authorities
13:22, 10.01.2026
Another Russian drone attack leaves many consumers in Dnipropetrovsk region without electricity - Ukrenergo
14:59, 07.01.2026
Some 423 MW of new balancing capacity already added to power system after first 2 special auctions – Ukrenergo
13:27, 02.01.2026
Ukrenergo officials suspected of seizing electricity without actual payment - PGO
13:51, 29.12.2025
LATEST
Moldova prepares to start negotiations with IMF on new cooperation program
21:12, 13.01.2026
MHP subsidiaries provide guarantees for potential new bond issue of up to $1 bln
21:00, 13.01.2026
JYSK indexes store employees' salaries in Ukraine by 15%
19:50, 13.01.2026
Russia attacks 15 critical infrastructure facilities in Ukraine today – official
18:55, 13.01.2026
YASNO CEO: Kyiv's right bank now facing left-bank level outrages