Protective arch should be placed over destroyed Chornobyl power unit by mid-November - Ukrainian environment minister
Efforts to complete the construction of an arch-shaped protective structure and place it over the destroyed fourth power generating unit of the Chornobyl nuclear power plant (NPP) are proceeding according to schedule, Ukrainian Ecology and National Resources Minister Ostap Semerak said on his Facebook page.
"I hope we will complete the process of its [the arch's] placement in 168 days [by the middle of November]," he said.
Donor countries have transferred money to an account at the European Bank for Reconstruction and Development in order to finish the construction of a spent nuclear fuel storage facility at the Chornobyl NPP, including EUR 1.4 million from Ukraine, the minister said.
Advertising
Advertising
MORE ABOUT
Ukraine continues repairs to Chornobyl confinement structure after drone attack – IAEA
11:44, 01.05.2025
Today marks anniversary of Chornobyl disaster
11:04, 26.04.2025
Intl cooperation fund allocates EUR 400,000 to assess damage to Chornobyl's New Safe Confinement
11:09, 04.03.2025
Ukraine, intl partners seeking solutions to restore Chornobyl NPP confinement – minister
19:51, 20.02.2025
Zelenskyy, his wife pay tribute to liquidators of Chornobyl disaster in Slavutych
19:12, 26.04.2024
LATEST
Ukraine's State Agency revises claims about UAH 6.6 bln road through Bukovel
20:30, 05.12.2025
G7, EU countries considering complete ban on oil transportation from Russia instead of price cap – media
20:29, 05.12.2025
Intl support for humanitarian demining since 2022 reaches nearly $1.5 bln – Economy Minister
19:42, 05.12.2025
Eighty-three candidates apply for four Energoatom Supervisory Board seats
14:02, 05.12.2025
Vodafone Ukraine announces another buy-out of eurobonds for $1.16 mln